Winslow Route 66 sign2

During their most recent council meeting, the Winslow City Council approved the following changes to current fees:

Pool admission adults from $2 to $2.50, senior pool admission from $.75 to $1, 18 visit pool pass for adults from $30 to $36, senior 18 visit pool pass from $10 to $15, 18 visit family pass from $25 to $30.

Girl Scout house rental is going from $80 to $100 per day and the Route 66 Plaza is going from $50 to $100 a day to rent.

Consolidated cemetery fees, removing the separate cost for children plots. New plot prices are going from $450 to $550 for in-county residents and from $900 to $1,800 to non-residents. Setup costs will rise from $100 to $150.

Bulk water rates will go from $5 to $8.25 per 1,000 gallons and right-of-way asphalt repair will go from a flat fee of $400 to $11 per square foot.

Resident waste will increase from $31.95 to $33.55 monthly and an additional toter will increase from $11 to $11.55 per month.

Septage disposable will now be priced by the total capacity of the tank at $0.15 a gallon.

The council also approved the following new fees:

Fire alarm and detection system plan review and inspections, $350 for new installations under 5,000 sq. ft., $400 plus $0.005 per sq. ft. for installations 5,001 sq. ft. and over; modifications, $100 for one to six devices, and $150 for seven or more devices.

Automatic fire sprinkler system plan review and inspections, $350 for new commercial installations under 5,000 sq. ft., $400 plus $0.005 per sq. ft. for installations 5,001 sq. ft. and over; modifications, $100 for one to 50 sprinklers, $150 for 51 or more sprinklers.

Residential (13D/R/M) sprinkler systems, $200 for new installations, $100 for modifications or additions.

Alternative fire extinguishing systems, $300 for new installations including foam, CO2, clean agent, chemical, etc.; commercial cooking hood single systems, $250; fire pumps new or modified installations, $450.

Spray booths and dipping plan reviews, $175 for pre-manufactured booths, $350 for non-pre-manufactured booths.

Fire department access permanent installations not associated with new projects, $100 per access gate.

Liquid petroleum gas plan review, $100 for new tanks 250–500 gallons, $150 for tanks 501 gallons or more.

High-piled combustible storage plan review, $100.

Violation fees apply for no approved plans on site or missed scheduled inspections with a 30-minute wait, failure to install per approved plans without prior approval, and failure to pre-test fire protection systems for acceptance.